In June, when federal money for the Mountain's Edge Regional Park expansion was announced, 8NewsNow reported that Clark County had not yet announced an exact construction timeline.
The county has a schedule now. The plan behind it shapes the next three years at the park on Mountains Edge Parkway. The new recreation center and roughly 55 acres of new parkland will be built at the same time by one contractor, and all of it is scheduled to open on the same day. Nothing new will open in stages along the way. The park you use this winter is the park you will have until the whole project opens.
A builder was picked on November 17
On Tuesday, November 17, the Clark County Board of Commissioners voted unanimously to approve a preconstruction services contract with CORE Construction. The contract covers the Mountain's Edge Recreation Center and Mountain's Edge Regional Park Phase II, as KSNV reported the next day.
The county's agenda file for the vote shows how the county chose a builder. The request for proposals was advertised on June 16, 2026, and six general contractors responded. One proposal was set aside because it was submitted on the wrong form. A five-member review committee first ranked Sletten Construction of Nevada at the top of the written proposals. After oral presentations from three finalists, the committee moved CORE Construction to first and recommended it.
The first dollars are small. The contract starts with preconstruction services only: $196,000 from the county's Recreational Capital fund and $120,000 from SNPLMA grant money, for a total of $316,000. The full budget was approved earlier. In two votes, on October 17, 2023 and March 5, 2024, commissioners approved up to $89.6 million for the recreation center and Phase II together. This month's vote gave that money a builder. The project is designed by Knit Architecture and managed by Clark County's Department of Real Property Management.
What the 55 acres add
Most of the outdoor work is paid for by a federal grant. Through the Southern Nevada Public Land Management Act, the U.S. Department of the Interior awarded Clark County $43,618,352 for Mountain's Edge Regional Park. The county's grant announcement lists four parts for the roughly 55 acres:
- A soccer complex
- A pickleball complex
- A community botanical garden
- A rerouted walking loop that connects the new areas to the rest of the park
The trail change matters to anyone who walks the park every day. The plan calls for realigning the existing loop, so a regular route may follow a different path once the expansion opens. Commissioner Justin Jones, who represents District F, said the new phase would give the park activities for soccer players, pickleball players and people looking for a quiet stretch in the botanical garden.
Park visitors who spoke with 8NewsNow in June had a range of views. One raised questions about habitat and water use, and another welcomed the indoor recreation center and the pickleball courts. The same federal funding package included money for the county's Multi-Species Habitat Conservation Plan.
The building, and the pool that isn't in the plan yet
The early floor plans for the recreation center include flexible classrooms and community programming space. The site plan also sets aside space and grading for a possible future aquatic center. A pool is a possibility the design allows for. It is not part of the current project.
The published plans also have no splash pad. In the June 8NewsNow story, one parent named a splash pad as the feature they would most like to see, for the hottest months. County documents describe the design as still in progress, so a resident who wants to weigh in on features has time. The county says it will share community outreach opportunities and final renderings during the final design phase.
Why it all opens at once
The county is building the recreation center and the park expansion together under a single contractor. Its stated reasons are efficiency and less disruption for people using the park. That means one construction period for the whole project, with no early soccer fields while the building is still unfinished.
Here is the county's schedule. Every date on it is an estimate:
- Fall 2027: final design completed in September or October, then Guaranteed Maximum Price approval in October or November.
- Winter 2027/2028: groundbreaking in December 2027 or January 2028, starting a construction period of about 24 months.
- Winter 2029/2030: construction substantially finished and a grand opening in December 2029 or January 2030.
As of this Thanksgiving, groundbreaking is about 13 months away, and the opening is about three years out. The November contract is only for preconstruction work. Construction dollars come later, after the price is set in late 2027.
Indoor options until the center opens
Until the doors open, Mountains Edge households will keep using existing county facilities. Clark County lists these nearby:
- Desert Breeze Recreation Center, 8275 Spring Mountain Road: two gyms, a fitness room, classrooms and meeting rooms.
- Desert Breeze Aquatic Facility, at the same Spring Mountain Road address.
- Aquatic Springs Indoor Pool, 7025 South Fort Apache Road.
At the regional park itself, 8101 West Mountains Edge Parkway, the county lists playgrounds, large sports fields, trails and large picnic areas. Its two pavilions, Tortoise and Hare, can each be reserved for groups of up to 150 people through Clark County's park reservation system. For a birthday party or team gathering in 2027 or 2028, those two pavilions are the largest reservable group spaces at the park until the expansion opens.
December 12 at Exploration Peak
This winter, the Mountains Edge Master Association's main holiday event is at the neighborhood's other big park. Jingle & Mingle: Winter Fest runs Saturday, December 12, from 11 a.m. to 3 p.m. at Exploration Peak Park. The Association announced it on November 17, the same day as the commission vote. The program includes a Christmas maze, holiday field games, a petting zoo, photos with Santa at Santa's Workshop, and an appearance by the Grinch.
If you go, bring an extra toy. Winter Fest is a drop-off point for the LV Stuff the Bus Toy Drive, which benefits the Firefighters of Southern Nevada Burn Foundation. Every toy donated at the event earns a $5 coupon for any participating food truck. The Association also has a registration page for the event. If you've only used Exploration Peak for the climb to the top, the park has more to it. Our earlier post on the Skill Shot wall most Mountains Edge residents have never used covers a few of its features.
If you'd like to talk through how a 2030 recreation center and a bigger regional park fit your own plans in Mountains Edge, whether you're staying for the long run or thinking about your next move, The LeJon Jenkins Team is glad to share what we're watching on the southwest side. Let's Connect.